Ramp Slope Calculator

In short: slope is one number wearing three outfits: a ratio, a percent and an angle. A 24-inch rise at the ADA maximum of 1:12 needs 24 feet of run — an 8.33 percent grade, an angle of 4.76 degrees, and a ramp surface just over 24 feet long. Enter your rise and a standard, or your own run, and the calculator translates between all three.

Ratio, percent and angle

A slope can be stated three ways, and confusion between them causes real building errors. As a ratio, 1:12 means one unit of rise for every twelve units of run — the language of building codes. As a percent, the same slope is rise / run x 100 = 8.33 percent — the language of roads and driveways. As an angle it is arctan(1/12) = 4.76 degrees — the language of geometry. They are not interchangeable numbers: 100 percent grade is 45 degrees, not vertical, and a 1:12 ramp is not a 12 percent grade. This calculator always shows all three, so whichever language your code, your contractor or your drawing uses, you can check it against the others.

Ramp length is the third dimension people forget: the sloped surface is the hypotenuse, sqrt(rise squared + run squared). At gentle slopes it barely exceeds the run — 24 ft of run at 1:12 needs 24.04 ft of ramp — but it is the figure that orders material and fits the ramp between landings. Landings matter in the codes: the ADA limits a single ramp run to a 30-inch rise before a level landing is required, so a 36-inch rise is two runs and a landing, not one long ramp, however much garden you have.

The accessibility standards

The ADA's 1:12 maximum for new ramps is a compromise between independence and space: steeper than 1:12 and many wheelchair users cannot push themselves up it; the standard also allows 1:10 or 1:8 for very short rises in alterations of existing buildings (3 inches and 6 inches of rise at most, respectively). 1:16 is noticeably easier and is the slope designers prefer when the site allows it; 1:20 is gentle enough that the ADA does not classify it as a ramp at all, which removes the handrail and landing requirements that attach to ramps. Cross slope — the sideways tilt for drainage — is capped at 1:48. UK guidance (Approved Document M and BS 8300) works on the same principle with gradient limits tied to the length of each flight: 1:12 for short flights, easing to 1:20 for long ones.

For vehicles the numbers are different and steeper: driveway and car-park ramps commonly run 1:10 to 1:6 (10-16.7 percent), with transitions at top and bottom so cars do not ground out. Loading docks and trailer ramps go steeper still. The calculator includes a 1:8 option for those cases — flagged, because at 1:8 a ramp is a vehicle surface, not an accessible route, whatever it is labelled.

A worked example

A porch sits 24 inches above the path. At the ADA maximum 1:12: run = 24 x 12 = 288 inches = 24 ft; grade = 24/288 = 8.33 percent; angle = arctan(1/12) = 4.76 degrees; ramp length = sqrt(288 squared + 24 squared) = 289 inches, just over 24 ft. At the kinder 1:16: run 32 ft, grade 6.25 percent, angle 3.58 degrees. At 1:20: run 40 ft, grade 5 percent, angle 2.86 degrees. The trade is always the same — gentleness costs ground. Where the ground is not there, switchbacks with level landings are how real buildings buy the run in a smaller footprint.

Frequently asked questions

What does a 1:12 slope mean?

One unit of vertical rise for every twelve units of horizontal run — a step up of 1 inch needs 12 inches of ramp. As a percent grade it is 8.33 percent, and as an angle 4.76 degrees. It is the maximum slope the ADA allows for a new wheelchair ramp, and the most quoted ramp figure in building. Do not confuse it with a 12 percent grade, which is 1:8.33 — much steeper, and not an accessible slope.

How long must a ramp be for a 30-inch rise?

At the ADA maximum of 1:12, 30 x 12 = 360 inches = 30 feet of run, and 30 inches is also the maximum rise allowed in a single run before a level landing is required. At the gentler 1:16 it needs 40 ft; at 1:20, 50 ft. A rise above 30 inches therefore means at least two runs with a landing between them, and the total footprint is the runs plus the landing, not just the slope length.

How do I convert slope percent to degrees?

Degrees = arctan(percent / 100). An 8.33 percent grade is arctan(0.0833) = 4.76 degrees; a 100 percent grade is 45 degrees exactly. Going the other way, percent = tan(degrees) x 100. The two scales part company quickly: doubling the angle from 5 to 10 degrees nearly doubles the percent (8.7 to 17.6), but at 30 degrees the grade is already 57.7 percent, and at 45 it is 100.

What slope is too steep for a wheelchair?

Anything above 1:12 (8.33 percent) is beyond the ADA maximum for a new ramp, and in practice many users find 1:12 itself hard work over a long run, which is why 1:16 or 1:20 is preferred where space allows. Short existing rises have narrow exceptions — 1:10 for up to 3 inches of rise, 1:8 for up to 6 — but those are alteration allowances, not design targets. A powered chair copes with more; a manual chair and wet weather cope with less.

What is the difference between slope and pitch?

They describe the same steepness in different trades. Slope here is rise over run as a ratio, percent or angle, used for ramps, roads and ground. Pitch, in roofing, is traditionally rise in inches per 12 inches of run — a "6/12 pitch" is 6 inches of rise per foot of run, which is a 1:2 slope, 50 percent, 26.6 degrees. Same geometry, different dialect; this site has a separate roof pitch calculator for the roofing version.

Related tools

Standards checked on 24 November 2026 (ADA 2010 Standards; UK Approved Document M gradients). Local codes vary — confirm with your building authority for permitted work. Everything is calculated in your browser — nothing you type is sent anywhere.