Concrete Calculator
Volume is geometry; the art is in the allowances
The maths is the easy part: rectangles multiply, cylinders use πr²h, and 27 cubic feet make a cubic yard. Everything that goes wrong on pour day lives in the gap between the paper shape and the real one. Subgrade is never perfectly level, so a "4-inch" slab averages 4.4; trenches bell out below the string line; formwork bows under wet concrete's considerable pressure. The trade's answer is the 10% overage built into this calculator's second column — not pessimism but statistics, because the failure mode is asymmetric: leftover concrete costs a few bags, while running short mid-pour costs a cold joint (a permanent weak seam where the second batch meets the first) or a short-load delivery fee that can exceed the concrete itself.
The second decision is bags versus ready-mix, and it has a fairly sharp boundary. Below about half a cubic yard, bags win: no delivery fee, no minimum, work at your own pace. Around one yard the economics flip — 45 to 60 heavy bags, each to be lifted, opened, mixed and placed inside its working time, against one truck that empties in twenty minutes. At two yards and beyond, bags are rarely rational unless access forbids a truck. There is also a quality argument: site-mixed bags vary batch to batch in water content, and water is strength — every extra splash for workability is paid for in final psi, which is why the bag's printed water measure is a specification, not a suggestion.
Thickness deserves its reputation as the cheapest strength. A slab's bending resistance grows with roughly the square of its depth, so moving a driveway from 4 to 5 inches buys about 56% more strength for 25% more concrete — and moving to 6 inches doubles it. Reinforcement (mesh or rebar) does a different job — it holds cracks tight rather than preventing them — and control joints, cut or tooled every 8–12 ft, decide where the inevitable shrinkage cracks politely occur. None of that changes the volume arithmetic above, but all of it decides whether the volume you pour is still a slab in ten years.
Before the truck or the bags arrive: the 20-minute checklist
Volume errors are usually discovered at the worst possible moment, so run the checks while they are still cheap. Re-measure the excavation, not the plan — the hole as dug is the hole you must fill, and it is reliably larger than the drawing. Confirm the thickness with a string line across the forms, not at the edges where the subgrade is tidiest. Check that the bag count you bought is the with-waste column, and stage the bags under cover: a bag that has taken rain is a bag already setting in its paper. If a truck is coming, confirm the order in cubic yards, the arrival window and the chute's reach — a truck that cannot reach the forms turns 4 yards of concrete into 40 wheelbarrow trips against the clock. Finally, decide in advance where the surplus goes: a few pre-built small forms (a step, a pad for the bins) convert the overage you wisely ordered from waste into the cheapest concrete you will ever place.
Worked examples
The patio slab. 10 × 10 ft × 4 in = 33.33 cu ft = 1.23 cu yd (0.94 m³). Bags: 56 × 80 lb / 75 × 60 lb / 112 × 40 lb; with 10% waste: 62 / 82 / 123.
The fence line. Eight post holes, 12 in diameter × 3 ft deep: 2.36 cu ft each, 18.8 cu ft total → 42 × 60 lb bags (with waste, 47).
The footing run. 40 ft of trench, 12 in wide × 12 in deep: 40 cu ft = 1.48 cu yd — firmly ready-mix territory if a truck can reach it.
Bag yields — the reference numbers
| Bag size | Yield per bag | Bags per cubic yard | Bags per m³ |
|---|---|---|---|
| 80 lb (36.3 kg) | 0.60 cu ft | 45 | 59 |
| 60 lb (27.2 kg) | 0.45 cu ft | 60 | 79 |
| 40 lb (18.1 kg) | 0.30 cu ft | 90 | 118 |
Frequently asked questions
How much concrete do I need for a 10×10 slab?
At the standard 4-inch thickness: 10 × 10 × ⅓ ft = 33.33 cubic feet = 1.23 cubic yards (0.94 m³). In bags that is 56 × 80 lb bags, 75 × 60 lb bags or 112 × 40 lb bags — and with the standard 10% waste allowance, 62 / 82 / 123. Past about a cubic yard, a ready-mix truck usually beats bags on price and always on effort.
How many bags of concrete are in a cubic yard?
By yield: an 80 lb bag makes about 0.60 cu ft, so a cubic yard (27 cu ft) takes 45 bags; 60 lb bags (0.45 cu ft) take 60; 40 lb bags (0.30) take 90. That is why bag maths gets painful fast — a 2-yard driveway apron is 90 heavy bags and a full day of mixing.
Why add 10% extra concrete?
Because the hole is never exactly the shape on paper: subgrade settles unevenly, formwork bows, trenches over-dig, and some mix stays in the wheelbarrow. Running short mid-pour is the expensive failure — a cold joint in a slab, or a second delivery fee that dwarfs the saved concrete. Ready-mix suppliers and bag counts both assume the overage; this calculator shows figures with and without it.
How deep should a concrete slab be?
4 inches for patios, paths and shed bases; 5–6 inches for driveways and anything a vehicle crosses; footings go below the local frost line, which is a code figure, not a preference. Thickness is the cheapest strength there is: doubling depth multiplies bending strength roughly fourfold, while the concrete volume only doubles.
How much concrete for fence post holes?
A 12-inch diameter hole 3 ft deep holds π × 0.5² × 3 = 2.36 cu ft — about five 60 lb bags per hole before waste. Eight posts: 18.8 cu ft, 42 bags. Post holes are where bag counts surprise people; the calculator's round-hole mode exists for exactly this.